Skip to main content
Ramakrishna Electrical Winding Works Logo
RK
Ramakrishna Electrical Winding WorksRamakrishna ElectricalWinding WorksServing since 1950
Who We Are
Services
Products
How We Deliver
Markets
View GalleryGalleryGet Quote

Footer

Ramakrishna Electrical Winding Works Logo
RK
Ramakrishna Electrical Winding WorksServing since 1950
ISO certification
Certification
Certification
Opp Boat Club, Pitapuram Road
Kakinada, Andhra Pradesh - 533003
info@rkelc.com+91 88423 74185

Company

  • About Us
  • Our Team
  • Heritage
  • Careers
  • Contact

Services

  • Repair & Rewind
  • Testing & Inspection
  • Engineering

Markets

  • Power & Renewables
  • Oil & Gas
  • Metals & Mining
  • Marine & Defence

Resources

  • Case Studies
  • Blog
  • FAQ
  • Gallery
  • Quality Assurance

© 2026 Ramakrishna Electrical Winding Works. All rights reserved.

Privacy PolicyTerms of Service

Major Generator Overhaul for 500 MW Thermal Power Plant

Emergency stator rewinding and rotor refurbishment for a 500 MW thermal power plant generator, completed 50% faster than the original outage window with zero safety incidents.

Power Generation & RenewablesIndiaLeading Power Generation Company

Power Generation & Renewables

Review the project background, diagnosis, intervention steps, standards, and results summarized below.

Project Background

What was the problem we solved?

A base-load 500 MW thermal power plant experienced insulation failure on a main generator during a planned outage. The defect was more severe than initially identified, threatening to extend the outage beyond the grid-committed window and risking penalties and lost generation revenue.

Assessment & Diagnosis

How was the diagnosis and assessment conducted?

1

On-site visual inspection and partial discharge indications highlighted severe insulation ageing on several stator slots.

2

Offline tests (IR, PI, tan-delta, winding resistance) confirmed insulation degradation beyond acceptable limits.

3

Bore-scope inspection identified localised hotspot damage and partial core lamination distress.

4

Root cause analysis linked the failure to thermal cycling, historical overloads and aged insulation system.

Execution & Intervention

What was the intervention and execution approach?

1

Developed an accelerated outage programme in coordination with plant operations and grid commitments.

2

Executed complete stator rewinding with upgraded Class F/H insulation system and improved slot support.

3

Refurbished rotor including rotor winding checks, balancing, and refurbishment of critical components.

4

Performed core flux testing, EL-CID test and corrective work on affected core laminations.

5

Implemented enhanced cooling and ventilation improvements as part of the rewind design.

Quality & Standards

What standards, quality, and safety measures were applied?

1

All work executed under ISO 9001:2015 Quality Management System.

2

Testing and acceptance criteria aligned with IEEE 43, IEEE 56 and IEC 60034.

3

Site safety procedures aligned with ISO 45001 and plant-specific HSE requirements.

4

Final testing performed under NABL-accredited laboratory supervision for key measurements.

Measurable Results

What were the measurable results?

Project completed approximately 50% faster than the originally forecasted extended outage duration.

Zero safety incidents recorded throughout the project, including confined-space and high-voltage activities.

Stator insulation test values improved significantly post-rewind, with tan-delta reduced from approximately 0.015 to around 0.004 and PI improving from ~1.5 to ~3.5.

Generator efficiency improved by approximately 15% compared to pre-failure baseline, with operating vibration maintained within OEM limits (< 20 µm on critical bearings).

Plant returned to grid within the committed window, avoiding penalties and unserved energy costs.

Have a similar challenge?

Talk to RKELC about how we can apply the same engineering approach to your rotating equipment.

  1. Home
  2. Case Studies
  3. 500 MW Generator Overhaul